WandiProgress
  • Home Page
    • Snake Bite
    • Bushfire Advice & Preparation
    • First Aid Defibrillator
    • Busy Bee 2021
    • Resource Centre Upgrade
    • Neighbour Day >
      • Neighbour Day 2023
  • Committee & Latest Minutes
    • Wandi Progress Assoc. Member Achievement
    • 25th anniversary of the WPA
    • A brief history of the WPA
    • Past Committee Minutes
  • Our Projects
    • RESOURCE CENTRE MURAL
    • "The Pavilion" New Building Progress
    • Hope Valley Primary School Relocation
  • Wandi Landcare
    • Lake Magenup Walk Trail
    • Landcare Rehabilitation 2021
    • WANDI NATIVE FLORA
    • Wandi Weeds
    • Past Landcare Projects
  • Community
    • Cleaning Up Wandi
  • Facilities
    • Wandi Community Hall
    • Clubrooms
    • Tennis
    • Playground & BBQ
    • Pavilion
    • Resource Centre
    • Shed
  • Wandi Warbler
  • Wandi Playgroup
  • Wood Working Clubs
    • Wandi Woodturners >
      • Monday Woodturning Group
      • Wednesday Woodturning Group
      • Dust Extraction Installation
      • Demonstrators Wandi Club
      • Progress Jack de Vos Lathe
      • Woodworking Projects >
        • Woodworking Projects - Trivet
        • Woodworking Projects - Tulips
        • Woodworking Projects - Salt & Pepper Grinders
      • Wandi Woodturners - Contacts
      • Wandi Woodturners Club History
    • Marquetry Club of WA
    • Scroll Saw Club of WA
    • WA Carvers Guild Wandi
  • Equestrian Centre
  • Medieval Groups
  • Smithy's Boxing Gym
  • Contact Us
  • Application Forms

NEW WANDI FACILITY UNDERWAY
JANUARY 2015
​COMPLETED SEPTEMBER 2015

Once our new building was completed four permanent user groups moved in -
  1. ​Wandi Woodturning Club
  2. WA Scrollsaw Club
  3. Southern Districts Triton Club
  4. Women Working In Wood Group
​We also have other groups using the Recreation room -
  1. ​KONGA
  2. Horse Riding Fitness
  3. Sword Point formerly GLECA
  4. Forward in Faith  Ministries  International Church
The Wandi Progress Association began discussions with the Town of Kwinana in 2009 to construct new facilities to house permanent clubs in the ever expanding Wandi Community Centre.
Now the Town is a City and the WPA's plan to develop the community site for the benefit of user groups is finally taking shape. Construction will take about 38 weeks, completion is around October 2015.
Once construction is complete the main beneficiaries will be the Wandi Woodturning Group a branch of the Woodturners Association of WA, Scrollsaw Club of WA and the Southern Districts Triton Club. A large recreation room will allow other groups to use the facilities and it's proximity to the Magenup Equestrian Centre will make it ideal for equestrian functions.
Picture
Picture
Site clearing was in full swing on Monday 19th January 2015
Yellow sand fill, getting the site ready for compaction 24 January 2015
Picture
Picture
Site view from car park 24 January 2015 This will be the front of the building when finished.
Picture
Plumbers at work, some concrete foundations in, mesh on site for slab 16 February 2015
Picture
Concrete pumped in and levelled, photo taken at 9am 20 February 2015
Concrete walls being poured 31 panels in all 8.30am 11 March 2015
Picture
Picture
Concrete wall erected 30th March 2015 photo taken 1st April 4 pm 2015
Site view from car park 1st April 4pm 2015 This will be the front of the building when finished.
Picture
Picture
Area cleared for Biomax leach drains at the base of the viewing mound on the oval and arena, cleared 9th April.
Work behind the Hall installing the Biomax concrete waste processing tanks, six will be placed in a line with their tops exposed for maintenance. Leach drains will extend south from here. 13 April 2015.
Picture
Picture
View from car park, paint going on. 5 June 2015
Ceilings ready to be installed in amenity and wet areas.
Front view of building more paint and colours. 5 June 2015.
Building at lock up stage, some internal fit out completed with wet areas ready for tiling.
Exhaust air extraction and hot water solar panels installed on roof.

7 July 2015
Ceilings installed.
Mezzanines over storerooms installed in workshop.
Painting almost complete internal and external.
Tiling well underway and almost complete.
Amenity cupboards installed.
Electrical install almost complete.
Plumbing almost complete.
Picture
Picture
29 July 2015
Veranda concrete complete.
Tiling complete.
Plumbing and electrical fit out ongoing. 
Our new building now has a name "THE PAVILION", sign installed 26/08/15
Anti Graffiti sealer applied during this week, inside complete.

BUILDING HANDOVER WAS HELD ON 14 SEPTEMBER 2015

City of Kwinana, Shelford Construction, Architects Hodge Collard Preston and the Wandi Progress Association representatives all participated in a formal handover of the Pavilion to the Wandi Community at 10 am on Monday the 14th September. 

Once the handover was complete the Wandi Woodturning Club members and Wandi Scrollsaw Club made up a large working party of volunteers to seal the workshop concrete floor with an industrial non skid finish. The job took two mornings and included floor scraping and cleaning with the cutting in of sealer up to the walls and the rolling of the large floor and storeroom spaces. As there was a little left over the Scrollsaw Club offered to reseal there old work space floor in the Club Rooms, well done.
Monday the 21st September will see the contractor begin sealing the Recreation and amenity rooms with a moisture barrier and Tuesday the parquetry floor will go down. This is a large job taking 10 days, once complete clubs will be able to move into their allocated areas.

Website by JPS IT Solutions